Road Construction Summary:
The Village has contracted
Tri County Paving to replace the asphalt on the following streets:
School Street (Madison Street to Williams Street)
Williams Street (School Street to S Pardee
Street)
Howard Street (Madison Street to Williams Street)
Herman Street
Sunnyview Lane (Hubbell Street to Maunesha Drive)
Additional work includes:
Storm sewer construction on Sunnyview Lane.
Construction of the new parking lot adjacent to
Village Hall.
Spot curb and gutter repairs on School Street,
Williams Street, and Porter Street.
Please note that residents
affected by the curb and gutter work may temporarily lose access to their
driveways. The Village's contractor is expected to coordinate directly with
impacted homeowners regarding driveway access during construction.
Tentative 2026
Construction Schedule
Tuesday, August 4: Farnham House demolition.
Friday, August 7: Pulverization and grading of Sunnyview Lane.
Monday, August 10: Begin storm sewer work on Sunnyview Lane
(approximately three days), with grading and paving to follow shortly
afterward.
Monday, August 10: Begin curb and gutter removal and replacement on
School Street, Williams Street, and Porter Street (approximately ten
days).
Again, residents affected by
the curb and gutter work may experience temporary driveway closures. The
contractor should coordinate directly with those homeowners.